See how better workflows and stronger risk controls can protect time, capacity and margin.
A field instruction needs a traceable path into an approved scope, a current budget, and a billable record.
Potential net recovered value / year
After recurring control costs.
Research-based composite. Business figures, savings and risk ratings are modeled assumptions. Proposed controls have not been validated with a business.
The proposed bottleneck is the unowned handoff between field identification, commercial review and billing release. A change can be physically complete while administratively invisible. Improving quote speed alone will not correct an approval that never reaches billing.
Connect every change to evidence, authorized direction, an updated budget and a billing record.
Proposed workflow: make the next action and responsibility explicit.
| Hypothesis | Evidence to inspect | Proposed test |
|---|---|---|
| Changes are never recorded | Match field diary and time tickets to change IDs. | Sample ten extra-work events from completed jobs. |
| Proposals wait for complete backup | Time-stamp identification, pricing and submission. | Separate missing evidence from PM workload. |
| Approval is not transmitted to billing | Trace approved changes to budget and next invoice. | Reconcile all approvals on two active projects. |
| Nonrecovery has another cause | Separate invalid scope, nonpayment and documentation failure. | Interview PM and billing using dispute reason codes. |
| Measure | Calculation | Modeled implication |
|---|---|---|
| Eligible change value | 15 changes/month x $2,400 | USD 36,000/month |
| Baseline billed value | 82% x $36,000 | USD 29,520/month |
| Target billed value | 94% x $36,000 | USD 33,840/month |
| Bottleneck removed | Complete record moves through a defined owner | Unapproved work stays visibly unresolved |
| Change ID / value | Evidence and status | Next action / owner |
|---|---|---|
| CO-017 / $2,400 | Directed; photos + hours complete | Price and submit / PM / next day |
| CO-018 / $3,100 | Approved; budget not updated | Enter + advise billing / PM / today |
| CO-019 / $1,700 | Billed; collection outstanding | Follow agreed terms / billing lead |
Audit ten changes; map authority and billing cutoff requirements.
Evidence: Agreement on eligible population and baseline recovery.
Pilot one change ID and evidence record on two jobs.
Evidence: At least 90% same-day capture; all approvals traceable.
Review aging and pending direction twice weekly.
Evidence: No approved item missing from budget reconciliation.
Follow invoices through collection and credit adjustments.
Evidence: Matched change cohorts; mature collection outcomes.
| Measure | Definition | Target | Owner / review |
|---|---|---|---|
| Same-day capture | Changes logged same day / identified changes | At least 95% | Foreman / daily |
| Approval-to-budget time | Working days from approval to budget update | At most 1 day | PM / weekly |
| Eligible value billed | Billed eligible value / eligible change value | 82% to 94% | Billing / monthly |
| Collectible uplift | Incremental receipts net credits / incremental billings | Test 95% assumption | Billing / monthly |
Use change cohorts rather than comparing a busy month with a quiet month. Establish which scope is eligible, hold direct work cost constant, and follow the incremental billings through receipts and credits. A 30-day pilot validates process use; collection benefits may require 90 days or longer.
This models recovered collectible value from eligible extra work already performed. It is not payroll savings.
| Financial line | USD |
|---|---|
| Annual eligible value | $432,000 |
| Incremental billings | $51,840 |
| Expected collectible uplift | $49,248 |
| Recurring annual administration | $3,600 |
| Annual net collectible uplift | $45,648 |
| First-year net benefit | $32,540 |
Adjust the share of the modeled improvement achieved. Control and setup costs stay the same.
First year: 10 benefit months, less the full setup allowance. Results are illustrative, not a guarantee.
These inputs describe the 100% modeled case. The slider changes the share of the proposed improvement achieved.
| Illustrative assumption | Value | Units |
|---|---|---|
| Eligible changes | 15 | per month |
| Average eligible value | 2,400 | USD/change |
| Calendar months | 12 | months/year |
| Baseline billed share | 82% | fraction |
| Target billed share | 94% | fraction |
| Expected collection share of uplift | 95% | fraction |
| Recurring administration | 300 | USD/month |
| One-time implementation allowance | 5,500 | USD |
| Benefit months in first year | 10 | months |
Annual eligible value: 15 x $2,400 x 12
Incremental billings: $432,000 x (94% - 82%)
Expected collectible uplift: $51,840 x 95%
Recurring annual administration: $300 x 12
Annual net collectible uplift: Expected collections less administration
First-year net benefit: Annual net x 10/12 - $5,500
No acceleration of existing receivables, financing benefit, new sales or automatic full collection is counted. The 95% collection assumption applies only to incremental billed value. Actual write-offs, concessions and additional direct costs reduce the result.
The dispute example describes a mechanism already represented by the recovery-rate model. Its expected-loss reduction is explanatory and must not be added to annual collectible uplift.
Eight modeled risks. Assessment horizon: one six-month project.
Current ratings are scenario assumptions. Select a risk to see its mitigation, owner and response.
Each number matches a risk in the register. Select an occupied cell to open a risk.
Higher likelihood and impact move a risk toward the top right. The Target view shows conditional ratings after the proposed controls.
Where several risks share a cell, it opens the first listed risk. All remain available in the register above.
A large, legitimate scope change becomes a documentation dispute on one project.
| Scenario | Probability × event loss | Expected loss |
|---|---|---|
| Before | 40% × $25,000 | $10,000 |
| With proposed controls | 20% × $25,000 | $5,000 |
| Expected-loss reduction | Before less after | $5,000 |
| Separate mitigation cost | Over this risk horizon | $1,000 |
| Net modeled risk benefit | Reduction less mitigation cost | $4,000 |
The $25,000 event impact represents unrecovered eligible value after direct work costs have already been incurred. Probabilities are assumed, not derived from public posts.
The dispute example describes a mechanism already represented by the recovery-rate model. Its expected-loss reduction is explanatory and must not be added to annual collectible uplift.
Score = likelihood × impact, each rated from 1 to 5. Scores 1–5 are Low, 6–11 Moderate, 12–19 High and 20–25 Critical. These are scenario judgments over the stated assessment horizon.
Likelihood: 1 below 5%; 2 from 5% to below 20%; 3 from 20% to below 40%; 4 from 40% to below 70%; 5 at least 70%. Impact: 1 below $1,000; 2 below $5,000; 3 below $20,000; 4 below $75,000; 5 at least $75,000 or potentially severe safety consequences. Impact-5 safety or technical issues require specialist review regardless of score.
Public discussions informed the problem selection. LeanLine Advisory developed the composite scenario, diagnosis and proposed controls. All company profiles, financial inputs and risk ratings are illustrative assumptions. The sources do not establish an industry-wide ranking of these issues.
Start with a Free Business Bottleneck Diagnostic. Bring the problem you can see.